  • Communication Equipment Power Supply Overview
  • This article provides the basic requirements and links to the instructions for replacing a power supply.   Current Power Supply Offerings Tigo offers two different AC Adapter Power Supplies (PS) w... See more
  • MLPE (TS4/ES) - Updating a Serial Number after Replacement
  • Contents: Overview Account Permission Web Browser Method EI App Method   Overview This article addresses how to change the serial number for a new Optimizer. If you are looking to change the ser... See more
  • Technical Documentation - Where to find Installation Manuals and Quick Start Guides
  • There are many resources that are available to help you design and implement a successful system! All installation manuals and Quick Start Guides can be found in the Technical Documentation section... See more
  • Can I run a TS4-A-O system without a TAP, CCA, or a connection to the Internet?
  • Full Deployment and System Discovery is required for all TS4-A-O systems, even though Optimization is functional with (or without) the Discovery process.  Blind Deployment is not recommended or sup... See more
  • Using the Cloud Connect Advanced Aux Port for Rapid Shutdown applications
  • Use Cases: Retain module-level information and third-party MODBUS data while the system is in rapid shutdown mode. There is a battery onsite. While in backup mode (the grid is out), if the bat... See more
  • Tigo Access Point (TAP) Communication Cable Types and Installation
  • Contents:  TAP Communication Cable Requirements Recommended Cable Types Maximum Cable Length Recommendations Using Ethernet Cables (Cat 5 / Cat 6) Installation Tips! Introduction This article ex... See more