Chapters
| Chapter | Stage | Purpose |
1 |
ASSESS | Understand the existing system and determine what still has value. |
2 |
DESIGN | Define the project boundary and verify compatibility before selecting replacement equipment. |
3 |
INSTALL | Document the system, correct existing deficiencies, and integrate new and existing equipment. |
4 |
COMMISSION | Verify configuration, communication, Rapid Shutdown, monitoring, and production. |
5 |
EXPAND | Add new capabilities now or prepare the repowered system for future upgrades. |
|
The Repowering Playbook creates and manages the opportunity. The Repowering Technical Playbook executes it. |
How to Use This Playbook
The RePowering Business Playbook explains how to identify, package, sell, and manage a repowering opportunity. This technical companion begins once the opportunity becomes a job. It is written for the point where an installer must evaluate an existing system, decide what can remain, design the replacement, complete the work, and prove the system operates as intended.
The technical workflow is intentionally simple:
ASSESS → DECIDE → DESIGN → INSTALL → COMMISSION → EXPAND
Three Questions for Every Stage
- What must be evaluated?
- What decision must be made?
- Which technical resource supports the next step?
For current product-specific requirements, procedures, compatibility information, and design tools, refer to the Tigo Help Center Repowering Guide and linked technical resources found in the Appendix.
Chapter 1: Assess the Existing System
| THE FIRST JOB IS UNDERSTANDING THE EXISTING SYSTEM, NOT REPLACING PARTS. |
Repowering rarely begins with a clean slate. The system may be ten, fifteen, or twenty years old. Documentation may be incomplete. Equipment may have been replaced, modified, or abandoned by a previous installer. Before designing anything new, build an accurate record of what is actually on site.
Start with evidence, not assumptions.
1.1 Pre-Site Information
Collect what is available before arriving on site. The goal is not to diagnose the system from the office; it is to arrive with enough context to conduct an efficient assessment.
- Reported system problem
- When the problem began
- Whether the issue is intermittent or consistently reproducible
- Available monitoring history
- Original plans, permits, and commissioning records
- Known inverter, module, MLPE, battery, and monitoring equipment
- Previous repairs or equipment changes
- Approved project objective from the homeowner or project owner
1.2 Initial Safety Screening
Before testing or modifying the system, determine whether it can be safely inspected and energized.
- Visible electrical hazards
- Damaged conductors or equipment
- Signs of overheating
- Corrosion or water intrusion
- Damaged connectors or exposed conductors
- Conditions that require correction before additional testing
| If the site cannot be safely tested, stop, correct the hazard, or escalate the condition before proceeding. |
1.3 Verify What Is Installed
Old drawings help, but nameplates, photos, and measurements help more. Document the actual equipment before assumptions about compatibility become part of the new design.
| MODULE | INVERTER | INTERCONNECTION |
| Make / model / ratings | Manufacturer / model / serial | Breaker / panel / point of interconnection |
The next design is only as good as the information collected before it.
1.4 Inspect What You Plan to Keep
Repowering is largely an exercise in deciding what still has value. Existing equipment should remain only after its condition, compatibility, and role in the new design are verified.
- PV modules: physical condition, ratings, connector type, mixed module types
- Array wiring: connectors, homeruns, conductor condition, wire management
- Grounding and bonding
- Roof penetrations and mounting condition
- MLPE type, condition, deployment, and placement
- Rapid Shutdown architecture
- Breakers, disconnects, service equipment, and conductor pathways
- Monitoring and communication equipment
Reuse is a design decision, not a default setting.
1.5 Electrical Evaluation
Perform the electrical checks required to verify that the existing array and balance-of-system behave as expected.
- String open-circuit voltage
- Polarity
- Measured versus expected voltage
- Current, where required
- Insulation resistance, where appropriate
- Grounding continuity
- Monitoring and production history
- Abnormal or inconsistent string behavior
1.6 The Assessment Must End in a Decision
Use the information collected during the assessment to determine the appropriate technical path forward.
|
REPAIR Correct a limited failure while retaining the existing system architecture. |
REPOWER Replace failed, aging, unsupported, or incompatible equipment. |
|
EXPAND Add storage, PV capacity, monitoring, or other capability. |
INVESTIGATE Additional testing or engineering review is required before proceeding. |
Pick the technical path before designing the solution.
Chapter 1 Deliverables
- Existing-system record
- Assessment findings
- Safety concerns
- Equipment reuse recommendations
- Repair, repower, expand, or investigate decision
- Information required for system design
Chapter 2: Design the Repowering Solution
| WHAT STAYS? WHAT GOES? WHAT GETS ADDED? WHAT IS OUT OF SCOPE? |
A repowering design must integrate new equipment with whatever remains from the original system. The design process begins by defining that boundary, then verifying compatibility rather than assuming the old array will simply plug into the new equipment.
Undefined boundaries create expensive surprises.
2.1 Define the Project Boundary
- Equipment that will remain
- Equipment that will be removed
- Equipment that will be replaced
- Equipment that will be added
- Existing deficiencies that must be corrected
- Work specifically excluded from the project
2.2 Will the Existing Array Work With the New Inverter?
This is the design question hiding behind every “simple” inverter replacement. Physical condition determines whether the modules are worth retaining; electrical compatibility determines whether they can be retained.
| EXISTING ARRAY | VERIFY | REPLACEMENT INVERTER |
| Module condition Ratings String configuration |
Cold Voc MPPT range Current limits String-to-MPPT assignments |
Applicable Tigo EI Inverter Service voltage Interconnection |
| Click HERE to download the Tigo EI String Sizing Tool | ||
- Minimum and maximum string length
- Maximum system voltage
- MPPT operating range
- Cold-temperature open-circuit voltage
- Maximum input current
- Parallel-string limitations
- Existing conductor suitability
Looking good enough to keep is only half the question. Prove the array works electrically with the replacement inverter.
2.3 MLPE and Rapid Shutdown: Rebuild the Architecture on Paper First
Legacy systems may contain older MLPE, no MLPE, or a Rapid Shutdown architecture that no longer fits the repowered design. Identify what exists, then determine what the repowered system must meet.
Determine:
- Existing MLPE manufacturer, model, generation, and function
- Whether the existing MLPE is required for inverter operation or is independent of the inverter
- Whether existing MLPE can remain with the proposed replacement inverter
- Whether existing MLPE must be removed or replaced
- Whether existing module-level equipment, connectors, or wiring creates compatibility constraints
- Whether optimization is required for the new design
- Whether module-level monitoring is required or desired
- Whether selective or full MLPE deployment is appropriate
- Applicable Rapid Shutdown requirements for the repowered system
- Whether existing Rapid Shutdown equipment can remain or must be replaced
- Required shutdown initiation method
- Expected array behavior during shutdown
- Labeling, testing, and verification requirements
Refer to Appendix A for an MLPE Decision flowchart.
| Do not assume the old Rapid Shutdown design applies to the new system. |
2.4 Communication and Monitoring Must Be Designed
Commissioning should confirm the design, not discover it. Know how many devices should be present, where communication equipment will be located, and how monitoring will reach the network before installation begins.
- Expected TS4 count
- Number of TAPs and TAP placement
- TAP-to-CCA assignments
- Roof planes, obstructions, and elevation changes
- Communication wiring pathways
- Internet and network requirements
- System ownership and user access
- Required site and equipment information
2.5 Can the Existing PV Breaker Stay?
A replacement inverter may have a different output rating than the original equipment. Do not assume that the existing PV breaker must change, and do not assume that it can remain. Evaluate the point of interconnection as part of the design.
- Existing PV breaker rating
- Panel and bus capacity
- Conductor ratings
- Interconnection method
- Whether changing the inverter output power (IPOC) is applicable
- Whether service equipment modifications are required
- Required documentation for the AHJ
Existing breaker reuse must be justified by design, configuration, and documentation.
2.6 GO Battery: Now, Later, or Not in Scope?
Repowering is the right time to decide on future expansion. If GO Battery is included now, design the complete system. If deferred, document the technical path so a future installation doesn’t start by undoing today's work. If proceeding with the battery, consult Chapter 5.
|
|
A deferred battery still needs a technical plan.
Chapter 2 Deliverables
- Final equipment list
- String and MPPT design
- MLPE and Rapid Shutdown architecture
- CCA and TAP design
- Electrical integration plan
- Monitoring plan
- Battery or battery-readiness plan
- Installation drawings and project documentation
Chapter 3: Complete the Repowering Installation
| THE FASTEST WAY TO LOSE TIME IS TO REMOVE THE ONLY EVIDENCE YOU HAD. |
Repowering work is different from new construction because the installer must preserve, identify, and integrate portions of an existing system. Document the original condition before removal, correct deficiencies that should not be carried forward, and use current product manuals for the exact installation procedures.
3.1 Document First. Disconnect Second.
Before equipment removal, capture both the detail and the context of the existing installation.
| DETAIL | CONTEXT |
| Photograph conductor terminations, labels, grounding, communications, and landed conductors. | Photograph equipment locations, conduit routing, disconnects, service equipment, and the overall BOS layout. |
Before disconnecting: document conductor terminations, equipment locations, and conduit routing.
- Confirm the approved design
- Verify equipment and materials
- Label conductors and circuits
- Record inverter settings and monitoring information
- Confirm shutdown and lockout procedures
- Protect equipment that will remain
3.2 Remove Existing Equipment Safely
- Follow the required shutdown sequence
- Account for stored energy
- Verify de-energization before removal
- Preserve reusable conductors and equipment
- Document unexpected site conditions
- Follow disposal, recycling, or return requirements where applicable
3.3 Correct Existing Deficiencies
| A REPOWER IS AN OPPORTUNITY TO CORRECT EXISTING DESIGN PROBLEMS, NOT REPRODUCE THEM. |
A repowering project should not inherit unsafe or noncompliant conditions simply because they existed before the new work began.
- Damaged conductors
- Improper wire management
- Grounding or bonding problems
- Connector issues
- Unsupported equipment combinations
- Incorrect breaker sizing
- Inadequate Rapid Shutdown architecture
- Water intrusion or corrosion
Correct existing deficiencies before incorporating existing equipment into the repowered system.
3.4 Use the Playbook for Sequence, the Manuals for Procedure
The playbook should guide the order of work and the decisions that belong to a repowering project. It should not duplicate current installation manuals.
SAFE REMOVAL → CORRECT DEFICIENCIES → INSTALL → INTEGRATE → QUALITY REVIEW
- Tigo EI Inverter
- TS4 MLPE
- CCA
- TAP
- Rapid Shutdown components
- Monitoring equipment
- ATS
- GO Battery, when included
3.5 Integrate Existing and New Equipment
- Conductor identification and polarity
- String and MPPT assignments
- Breaker and disconnect ratings
- Grounding and bonding
- Communication wiring
- Equipment labeling
- Required clearances
- Torque requirements
3.6 Installation Quality Review
Before energizing, compare the completed installation with the approved design.
- Inspect all terminations
- Confirm required labels
- Verify clearances
- Confirm conductors are protected and supported
- Confirm communication connections
- Record model and serial numbers
- Photograph the completed installation
- Document any as-built changes or unresolved issues
Common Repowering Installation Mistakes
- Assuming the existing design is correct
- Failing to label conductors before equipment removal
- Reusing equipment without verifying compatibility
- Treating the project exactly like new construction
- Overlooking legacy MLPE
- Incorrect MPPT assignments
- Inadequate TAP placement
- Reusing breakers or conductors without verification
- Skipping corrections because the condition existed before the repower
Chapter 3 Deliverables
- Installed system
- Updated equipment record
- As-built changes
- Installation photographs
- Pre-commissioning inspection results
- List of unresolved issues
Chapter 4: Commission and Verify the System
| INSTALLED IS NOT THE SAME AS OPERATIONAL. |
Commissioning proves that the repowered system is configured correctly, communicates as designed, performs the required safety functions, and produces as expected. The goal is not simply to get the inverter to turn on.
PRE-CHECK → POWER UP → CONFIGURE → DISCOVER → TEST RSD → VERIFY PRODUCTION
4.1 Pre-Energization Checks
- Mechanical installation
- Conductor terminations
- Polarity
- String voltage
- Grounding and bonding
- Breaker and disconnect positions
- Communication wiring
- Battery connections, where applicable
- ATS wiring, where applicable
4.2 Follow the Required Power-Up Sequence
Use the current product documentation for the required startup sequence. The technical playbook should show the sequence at a high level and point to the exact procedure.
- AC power
- DC power
- CCA
- EI Inverter
- ATS
- GO Battery
- Monitoring devices
4.3 Verify Firmware and Configuration
- Current required firmware
- Grid profile
- System operating mode
- Export or power-control settings
- Battery settings
- Meter and CT configuration
- Monitoring configuration
4.4 Discovery and Communication: Know What You Expect to Find
A successful discovery should confirm the design. If the design calls for 32 TS4 devices and the system discovers only 31, commissioning is incomplete.
- Expected TS4 count
- TAP communication
- CCA communication
- EI system communication
- Battery communication
- ATS communication
- Internet connectivity
- Portal visibility
4.5 Test Rapid Shutdown
- Initiate shutdown using the designed method
- Verify inverter response
- Verify TS4 response
- Verify CCA or transmitter behavior
- Confirm required voltage reduction
- Restore operation and verify recovery
- Confirm final Rapid Shutdown labeling
Rapid Shutdown is not verified until it is tested.
4.6 Verify Production
- String voltage
- String current
- MPPT behavior
- Inverter production
- Monitoring data
- Module-level data, where applicable
- Alarms and warnings
- Comparison with expected system behavior
A green light is not a commissioning test.
4.7 Complete the Technical Handoff
Keep this handoff technical. The Business Playbook already covers customer relationship strategy and ongoing service.
- Demonstrate system operation
- Confirm monitoring access
- Explain shutdown and restart procedures
- Explain backup behavior, where applicable
- Provide manuals and system documentation
- Record commissioning results
- Identify deferred work or known limitations
Chapter 4 Deliverables
- Commissioning record
- Verified device counts
- Rapid Shutdown test result
- Production verification
- Monitoring confirmation
- Final system configuration
- Technical handoff documentation
Chapter 5: Expand the Repowered System
| THE REPOWER IS THE RIGHT TIME TO MAKE THE FUTURE-EXPANSION DECISION. |
Some projects end with restored operation. Others create a platform for storage, additional PV, improved monitoring, or future household loads. Treat expansion as a technical design decision, not an afterthought.
5.1 Add Tigo GO Battery During Repowering
- Battery sizing and quantity
- EI Inverter compatibility
- ATS requirements
- Backup-load design
- Equipment location and clearances
- Communication requirements
- Commissioning sequence
- Permitting requirements
5.2 Prepare for Future GO Battery Installation
If battery storage is deferred, make reasonable accommodations during the repower so the future installation does not require unnecessary rework.
- Select compatible replacement equipment
- Reserve battery installation space
- Plan conduit pathways
- Plan communication pathways
- Reserve electrical capacity
- Identify future backup loads
- Document proposed equipment locations
- Record deferred design recommendations
DESIGN TODAY’S SYSTEM WITH TOMORROW’S BATTERY IN MIND.
5.3 Add PV Capacity
- Inverter capacity
- MPPT availability
- String compatibility
- Module compatibility
- Conductor capacity
- Interconnection limits
- Monitoring and MLPE requirements
- Permitting implications
5.4 Upgrade or Add MLPE
- Legacy TS4 compatibility
- Mixed-device limitations
- Monitoring additions
- Optimization additions
- Rapid Shutdown implications
- Discovery and commissioning requirements
5.5 Upgrade Monitoring
- Existing monitoring limitations
- CCA and TAP additions
- Network requirements
- Module-level visibility
- Account and ownership transfer
- Portal configuration
5.6 Document Deferred Expansion
- Equipment selected for future compatibility
- Reserved spaces
- Planned pathways
- Electrical limitations
- Future design assumptions
- Additional equipment required
- Conditions that must be reevaluated before expansion
Chapter 5 Deliverables
- Expansion design
- Compatibility confirmation
- Updated system drawings
- Updated equipment record
- Revised commissioning documentation
- Future-expansion recommendations
The Technical Repowering Mindset
| 1. Do not assume the existing system is correct. |
| 2. Do not reuse equipment until compatibility is verified. |
| 3. Do not leave until safety, communication, and production are verified. |
Technical Resources
Use the resources below for detailed procedures, product-specific instructions, and information that may change over time. Linking to the current source keeps this guide focused while ensuring you always have the latest requirements and instructions.
- Repowering a PV System with a Tigo Inverter: The Definitive Guide
- Repowering checklist
- Tigo EI Inverter installation and commissioning documentation
- Tigo string-sizing and design tools
- TS4, CCA, TAP, and Rapid Shutdown documentation
- EI Inverter Power Output Control (IPOC) application note
- GO Battery installation documentation
- Tigo Help Center articles
- Tigo Academy training
Appendix A: MLPE Decision Flowchart
APPENDIX B: REPOWERING FIELD ASSESSMENT WORKSHEET
Optional field resource for documenting the existing system and on-site assessment.
PROJECT INFORMATION
| Project / Site | Assessment Date | ________________ | ||
| Site Address | Installer / Company | ____________________________ | ||
| Primary Contact | System Age / | ________________ | ||
| Reported Problem | ________________________________________________________________________________________ | |||
| Project Objective | ________________________________________________________________________________________ | |||
EXISTING SYSTEM
| Equipment | Manufacturer / Model | Rating / Qty. | Serial / Notes |
| PV Modules | ________________________ | ____________ | ________________________ |
| Inverter | ________________________ | ____________ | ________________________ |
| MLPE / RSD | ________________________ | ____________ | ________________________ |
| Monitoring / CCA / TAP | ________________________ | ____________ | ________________________ |
| Battery / ATS | ________________________ | ____________ | ________________________ |
| Other | ________________________ | ____________ | ________________________ |
| PV Breaker | ________ A | Service Voltage | ____________ |
| Main Breaker | ________ A | Bus Rating | ________ A |
| Point of Interconnection | ________________________ | Monitoring History | ☐ Reviewed ☐ Unavailable |
INITIAL SITE & SAFETY CHECK
☐ Visible electrical hazards ☐ Damaged/exposed conductors ☐ Overheating ☐ Water intrusion/corrosion ☐ Damaged/mismatched connectors
☐ Grounding/bonding concerns ☐ Roof/mounting concerns ☐ Damaged modules ☐ Poor wire management ☐ Correct hazard before testing
Safety concerns / notes: ________________________________________________________________________________________________________
ARRAY & STRING MEASUREMENTS
| Str. | Mods. | Module Model | Expected Voc | Measured Voc | Current* | Polarity | Notes |
| 1 | ____ | ____________ | _____ V | _____ V | _____ A | ☐ + / − | ____________ |
| 2 | ____ | ____________ | _____ V | _____ V | _____ A | ☐ + / − | ____________ |
| 3 | ____ | ____________ | _____ V | _____ V | _____ A | ☐ + / − | ____________ |
| 4 | ____ | ____________ | _____ V | _____ V | _____ A | ☐ + / − | ____________ |
| 5 | ____ | ____________ | _____ V | _____ V | _____ A | ☐ + / − | ____________ |
| 6 | ____ | ____________ | _____ V | _____ V | _____ A | ☐ + / − | ____________ |
*Current where required or appropriate. Additional checks may include insulation resistance, grounding continuity, and abnormal string behavior.
Additional strings / measurements: ________________________________________________________________________________________
REPOWERING FIELD ASSESSMENT WORKSHEET — PAGE 2
EQUIPMENT CONSIDERED FOR REUSE
| Item | Acceptable | Concern | Replace | Notes |
| PV modules | ☐ | ☐ | ☐ | ________________________________ |
| Module connectors | ☐ | ☐ | ☐ | ________________________________ |
| Array wiring / homeruns | ☐ | ☐ | ☐ | ________________________________ |
| Grounding / bonding | ☐ | ☐ | ☐ | ________________________________ |
| Racking / mounting | ☐ | ☐ | ☐ | ________________________________ |
| Roof penetrations | ☐ | ☐ | ☐ | ________________________________ |
| MLPE | ☐ | ☐ | ☐ | ________________________________ |
| Rapid Shutdown equipment | ☐ | ☐ | ☐ | ________________________________ |
| Breaker / disconnects | ☐ | ☐ | ☐ | ________________________________ |
| Existing conductors | ☐ | ☐ | ☐ | ________________________________ |
| Monitoring / communications | ☐ | ☐ | ☐ | ________________________________ |
Insulation resistance performed, where appropriate: ☐ Yes ☐ No ☐ N/A Grounding continuity verified: ☐ Yes ☐ No
EXISTING MLPE / RAPID SHUTDOWN
| MLPE Mfr. / Model | ________________________ | Existing MLPE Qty. | ________ |
| MLPE Function | ☐ Optimization ☐ Monitoring | Rapid Shutdown | ☐ Yes ☐ No ☐ Unknown |
| Inverter-dependent MLPE? | ☐ Yes ☐ No ☐ Unknown | Expected to Remain? | ☐ Yes ☐ No ☐ Review |
Existing shutdown initiation method: ________________________________________________________________________________
Architecture / compatibility observations: ________________________________________________________________________________
MONITORING & COMMUNICATION
☐ Existing monitoring operational ☐ Internet/network available ☐ CCA identified ☐ TAP(s) identified ☐ Existing TS4 count documented
☐ System/account ownership identified ☐ Communication pathway documented
Concerns / notes: ________________________________________________________________________________________________
DOCUMENTATION CAPTURED
☐ Inverter nameplate ☐ Module model/nameplate ☐ MLPE/RSD equipment ☐ Electrical/service equipment ☐ Breaker / POI
☐ Conductor terminations ☐ Array/roof condition ☐ Monitoring equipment ☐ Equipment locations/conduit routing ☐ Existing labels ☐ Overall installation
ON-SITE ASSESSMENT
Equipment suitable for reuse: ________________________________________________________________________________
Equipment requiring replacement: ________________________________________________________________________________
Existing deficiencies requiring correction: ________________________________________________________________________________
Additional testing / engineering review required: ________________________________________________________________________________
PRELIMINARY TECHNICAL PATH
| ☐ REPAIR Correct a limited failure while retaining the existing system architecture. | ☐ REPOWER Replace failed, aging, unsupported, or incompatible equipment. |
| ☐ EXPAND Add storage, PV capacity, monitoring, or other capability. | ☐ INVESTIGATE Additional testing or engineering review is required before proceeding. |
Recommended next action / preliminary scope:
| Installer / Assessor | ____________________________ | Date | ________________ |